Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
The fourth phase (1 Kryshtaleva St.) is in the process of commissioning and connecting gas supply.
In the fifth phase (1-B Kryshtaleva str.), facade works (90% complete), interior finishing and electrical works (40% complete), finishing of the public usage places and staircases (15% complete), installation of elevators (70% complete), installation of apartment doors (80% complete), installation of technical doors (50% complete), installation of window and door structures (1-2 floors) are underway.
In the last part of the underground parking lot, the process of waterproofing is underway (50% complete).