LVIV RC "SHCHASLYVYI" FROM NOVABUDOVA CONSTRUCTION PROGRESS

02.06.2021

Currently, construction teams are working to ensure that the third building of the RC is getting closer to what the developer has promised investors. More specifically, in recent weeks:

  • the work on the floor slab on the 10th floor has begun;
  • the brickwork of the ventilation ducts has reached the level of 5-6 floors;
  • chimneys made of stainless steel screed, mounted from the basement up to the 5th floor;
  • masonry of walls and partitions has already begun both in the basement and at the level of the first floor.

There is still plenty of time until the end of work on the third building of the RC, but there will be several planned price increases per square meter. And soon enough, in June, such a planned stage will take place. Even after that, the price of the apartment will be favorable compared to the market value of real estate. However, it is most profitable to invest right now. This applies to both investing for resale or rent, and buying a home for your own living.