Herein we are telling you about the construction progress of the residential complex "Crystal Avenue" in Petropavlivska Borshchahivka.
In the second phase (11-A, Oksamytova St.) the installation and automation of barriers has been completed, and the installation of the parking access system is almost complete.
In the fourth phase (1, Kryshtaleva St.) installation of air conditioner baskets and installation of doors in public usage places is completed. Work continues on the decoration of the public usage places (40% complete), installation of apartment doors (50% complete), installation and commissioning of elevator equipment, installation of equipment in the control room.
In the fifth phase (1-B, Kryshtaleva St.) the brickwork of the walls is being completed (98% ready). Installation of windows (10% ready) and installation of sewage systems is in progress.