Here we summarize the August results of the residential complex "Shchaslyvyi" in Bihova Street, Lviv construction.

During the last month of summer, the builders focused mainly on interior work. In particular, they performed (and continue to perform) the following rage of work:

•work on the roof;

•internal plastering works;

•road construction from the side of Trakt Hlynyanskyi Street is also underway.

The electricity distribution, sewerage and sewage system were completely completed in August. The craftsmen will start the facade work soon.

We’d like to remind you that there are spacious 3-room apartments with a well-planned layout of 76.88 m2 in the 3rd building of the residential complex "Shchaslyvyi" left. The commercial premises, parking spaces in the underground parking lot and convenient storerooms are also on sale. 