The beginning of the month is the time to summarize the October results regarding the construction of our Lviv residential complex Shchaslyvyi in Bihova street and making plans for November.
So, in October, the builders completed the following amount of work:
•plumbing works for rolling cold water and heating pipes on floors 13-17;
•walls plastering on the 3rd, 5th, 7th, 8th, 11th floors;
•chimney covers arrangement;
•wet facade arrangement.
As for November, plastering of the walls on all floors except the first is scheduled to be completed this month; also to complete works on chimney caps; complete the work on arranging the roof covering; start arranging the ventilated facade.