CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (JANUARY 2025)

31.01.2025

Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.

The fourth phase (1 Kryshtaleva St.) is in the process of commissioning and connecting gas supply.

In the fifth phase (1-B Kryshtaleva str.), facade works are underway (90% complete), interior finishing and electrical works (15% complete), finishing of the public usage places and staircases (10% complete), installation of elevators (50% complete), and installation of apartment doors (50% complete). Preparations for the installation of boilers and radiators have begun.

The last part of the underground parking lot is being prepared for the membrane laying and the final layer of landscaping.

You can find out details about the construction, terms of purchase of housing or promotional offers by calling: +380960230310.