1
stage
60%
The first and second sections
• glazing has been fully completed;
• engineering, communication works and ventilation piping of the risers have been processed.
The third section
• monolithic works are underway on the 7th floor.
Underground parking lot
• general construction monolithic works are underway.
Shopping center
• arrangement of the facade;
• landscaping works;
• road marking and installation of road signs have been done;
• interior finishing works;
• fire protection works;
• installation of water and electricity supply.