Progress in construction

1
stage
100%
2
stage
100%
3
stage
95%
4
stage
65%
5
stage
50%
6
stage
8%
7
stage
3%

Progress in construction RC "Shchaslyvyi Grand", June 2026

First section

•  the house is commissioned

Second section

•  the house is commissioned

•  preparations are underway for the signing of key notarized agreements, and the process of connecting to the gas and electricity grids is in progress.

Third section

•  the installation of technical and apartment doors has been completed;

•  work is ongoing on the facade (98% complete), floor screed (95% complete), installation of railings (97% complete), finishing work (80% complete), landscaping around the building, and preparations for commissioning.

Fourth section

•  work is underway on the construction of walls and partitions (90% complete), window installation, the installation of water supply and sewer systems;

•  work has begun on the facade, and preparations are underway for roofing, plastering, and floor screeding.

Fifth section

•  monolithic work is underway on the 9th floor, including the construction of walls and partitions;

•  preparations for window installation have begun.

Sixth section

•  monolithic work continues on the basement level.

Seventh section

•  excavation work has been completed;

•  preparations for concrete work have begun.

Underground parking lot

•  the installation of the industrial flooring in Phase 1 of the underground parking lot has been completed;

•  work is underway on landscaping between Sections 1 and 2 (90% complete), the installation of fire protection systems in Section 5, electrical work, and preparations for applying road markings and finishing Phase 1.