
First section
• the house is commissioned
Second section
• the house is commissioned
• preparations are underway for the signing of key notarized agreements, and the process of connecting to the gas and electricity grids is in progress.
Third section
• the installation of technical and apartment doors has been completed;
• work is ongoing on the facade (98% complete), floor screed (95% complete), installation of railings (97% complete), finishing work (80% complete), landscaping around the building, and preparations for commissioning.
Fourth section
• work is underway on the construction of walls and partitions (90% complete), window installation, the installation of water supply and sewer systems;
• work has begun on the facade, and preparations are underway for roofing, plastering, and floor screeding.
Fifth section
• monolithic work is underway on the 9th floor, including the construction of walls and partitions;
• preparations for window installation have begun.
Sixth section
• monolithic work continues on the basement level.
Seventh section
• excavation work has been completed;
• preparations for concrete work have begun.
Underground parking lot
• the installation of the industrial flooring in Phase 1 of the underground parking lot has been completed;
• work is underway on landscaping between Sections 1 and 2 (90% complete), the installation of fire protection systems in Section 5, electrical work, and preparations for applying road markings and finishing Phase 1.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: JUNE 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.06.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (JUNE 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.06.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: JUNE 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
24.06.2026