Progress in construction

1
stage
60%
2
stage
40%
3
stage
30%

Progress in construction RC "Shchaslyvyi Grand", January 2025

The first and second sections

• facade works (bonded thermal insulation of the facade) and arrangement of internal engineering networks are underway.

The third section

• monolithic works are underway on the 8th floor.

Underground parking lot

• the floor slab is being arranged.

Shopping center

• tiles have been laid on the floor of the shopping center;

• work has been completed in the regular bathrooms and bathrooms for people with special needs;

• external and internal stained-glass windows are ready;

• installation of the ventilation and air conditioning system has been completed;

• landscaping of the territory has been completed;

• electricity and water supply systems have been completed.