Progress in construction

1
stage
60%
2
stage
40%
3
stage
30%

Progress in construction RC "Shchaslyvyi Grand", November 2024

The first section

• general construction works have been completed;

• facade works are underway (facade insulation is bonded), and works on the arrangement of internal engineering networks (storm and domestic sewage) are in progress.

The second section

• similar works are ongoing

The third section

• monolithic works are underway on the 7th floor.

The underground parking lot

• general construction works are underway