Progress in construction

1
stage
60%
2
stage
40%
3
stage
30%

Progress in construction RC "Shchaslyvyi Grand", July 2024

The first section

• brickwork of the walls continues; 

• internal partitions are being made;

• windows have been installed on the 2nd-4th floors.

The second section

• brickwork of walls continues.

The parking lot

• the upper floor slab has been poured.

Shopping center

• arrangement of decorative metal elements of the facade;

• flooring is in progress;

• all communications (plumbing, electricity) are ready.