First section
• the house is commissioned
Second section
• preparations for commissioning are underway.
Third section
• installation of heating and water supply systems has been completed;
• facade work (95% complete), floor screeding (85% complete), installation of railings (80% complete), installation of technical doors (95% complete), installation of fire protection systems (95% complete), electrical work (90% complete), installation of apartment doors (80% complete), and finishing work (30% complete) are ongoing.
Fourth section
• monolithic works are underway on the 8th floor and the technical floor, including the construction of walls and partitions (60% complete), preparation for window installation, and preparation for the start of installation work on the water supply and sewerage systems.
Fifth section
• monolithic works are underway on the 7th floor, including the construction of walls and partitions, and the fabrication of windows.
Sixth section
• work has begun on the foundation slab.
Underground parking lot
• work continues on landscaping between sections 1 and 2 (80% complete) and the installation of fire protection systems in sections 1-3 (95% complete);
• installation of fire protection systems has begun in section 5, and preparations for electrical work are underway.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: JUNE 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.06.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (JUNE 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.06.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: JUNE 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.