Progress in construction

1
stage
20%
2
stage
5%

Progress in construction RC "Shchaslyvyi Grand", Лютий 2024

The first section

• the walls of the 3rd floor have been poured and the slabs of the 3rd residential floor have been installed.

The second section

• a set of basement floor slabs has been completed;

• finished floor slab of the basement floor (set of reinforced frame of the basement floor slab, concrete pouring of the floor slab).

The third section

• the set of walls and columns of the basement floor has been started.