1
stage
100%

The first section
• the walls of the 3rd floor have been poured and the slabs of the 3rd residential floor have been installed.
The second section
• a set of basement floor slabs has been completed;
• finished floor slab of the basement floor (set of reinforced frame of the basement floor slab, concrete pouring of the floor slab).
The third section
• the set of walls and columns of the basement floor has been started.