Progress in construction

1
stage
80%
2
stage
70%
3
stage
50%
4
stage
20%
5
stage
15%
6
stage
0%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", April 2025

The first section

•  facade works (wet facade, fencing of cold passages of balconies), arrangement of internal engineering networks, roofing works are underway 

•  finishing works on the 8th-12th floors, plumbing works, and installation of the doors of the public usage places have begun.

The second section

•  facade works are underway (thermal insulation of the facade is bonded), and the arrangement of internal engineering networks;

•  preparations for plumbing works have begun.

The third section

•  monolithic works on the 12th floor are underway;

•  preparations for the installation of windows have begun.

Underground parking lot

•  waterproofing works and monolithic works of the entrance and part of the parking lot (section 3) are underway.