The first section
• facade works (wet facade, fencing of cold passages of balconies), arrangement of internal engineering networks, roofing works are underway
• finishing works on the 8th-12th floors, plumbing works, and installation of the doors of the public usage places have begun.
The second section
• facade works are underway (thermal insulation of the facade is bonded), and the arrangement of internal engineering networks;
• preparations for plumbing works have begun.
The third section
• monolithic works on the 12th floor are underway;
• preparations for the installation of windows have begun.
Underground parking lot
• waterproofing works and monolithic works of the entrance and part of the parking lot (section 3) are underway.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025