1
stage
60%
The first section
• earthworks have been completed;
• concrete preparation is poured in three sections;
• the foundation slab of the first section is poured.
• crane foundation construction is ready;
• work is being carried out with the vertical of the basement floor of the first section.
Shopping center "Shchaslyvyi Mall"
• metal construction, roofing and sandwich panels are finished.