Progress in construction

1
stage
20%
2
stage
5%

Progress in construction RC "Shchaslyvyi Grand", September 2023

The first section

• earthworks have been completed;

• concrete preparation is poured in three sections;

• the foundation slab of the first section is poured.

• crane foundation construction is ready;

• work is being carried out with the vertical of the basement floor of the first section.

Shopping center "Shchaslyvyi Mall" 

• metal construction, roofing and sandwich panels are finished.