The first section
• plumbing works, roofing, and plastering works have been completed;
• facade works (wet facade, fencing of cold balcony passages, installation of balcony fencing in apartments), installation of boiler room equipment, floor screed;
• preparations for finishing works, installation of elevators, installation of apartment doors, installation of aluminum structures of the basement have begun.
The second section
• facade works (bonded thermal insulation of the facade), arrangement of internal engineering networks, installation of water supply and sewerage systems, roofing, installation of doors of the public usage places, plastering works in the public usage places are underway.
The third section
• monolithic works have been completed;
• installation of window structures, construction of walls and inter-apartment partitions is in progress.
Fourth and fifth sectioins
• monolithic works on the basement are underway.
Underground parking lot
• monolithic works at the entrance/exit to the parking lot have been completed;
• sand backfilling is in progress.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025