First section
• finishing works have been completed and facade works are being finalized;
• electrical works, landscaping around the building, and the installation of radiators, heat and water meters are ongoing.
Second section
• floor screeding work has been completed;
• facade works, installation of internal engineering networks, interior finishing works, and installation of elevators and doors are ongoing.
Third section
• plastering works in public areas have been completed;
• facade works are ongoing (55% complete), installation of heating and water supply systems, floor screeding (20% complete), installation of window structures (95% complete), installation of railings (20% complete);
• installation of technical doors, fire protection systems, preparation for electrical works, installation of apartment doors, and finishing works have begun.
Fourth section
• monolithic works continue on floors 4-5;
• preparations for bricklaying walls and partitions have begun.
Fifth section
• monolithic works continue on floors 3-4.
Underground parking lot
• waterproofing between sections 1 and 2 has been completed.
• landscaping works between sections 1 and 2 are ongoing.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025