Progress in construction

1
stage
100%
2
stage
95%
3
stage
80%
4
stage
30%
5
stage
20%
6
stage
0%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", November 2025

First section

•  finishing works have been completed and facade works are being finalized;

•  electrical works, landscaping around the building, and the installation of radiators, heat and water meters are ongoing.

Second section

•  floor screeding work has been completed;

•  facade works, installation of internal engineering networks, interior finishing works, and installation of elevators and doors are ongoing.

Third section

•  plastering works in public areas have been completed;

•  facade works are ongoing (55% complete), installation of heating and water supply systems, floor screeding (20% complete), installation of window structures (95% complete), installation of railings (20% complete);

•  installation of technical doors, fire protection systems, preparation for electrical works, installation of apartment doors, and finishing works have begun.

Fourth section

•  monolithic works continue on floors 4-5;

•  preparations for bricklaying walls and partitions have begun.

Fifth section

•  monolithic works continue on floors 3-4.

Underground parking lot

•  waterproofing between sections 1 and 2 has been completed.

•  landscaping works between sections 1 and 2 are ongoing.