First section
• the house is commissioned
Second section
• facade work completed;
• the installation of internal engineering networks and preparations for commissioning are ongoing.
Third section
• installation of window structures has been completed;
• facade work is ongoing (75% complete), installation of heating and water supply systems, floor screeding (30% complete), installation of railings (20% complete), installation of technical doors, installation of fire protection systems (45% complete);
• electrical work has begun, preparation for the installation of apartment doors, preparation for finishing work.
Fourth section
• monolithic works continue on floors 5-6;
• preparations for bricklaying walls and partitions have begun.
Fifth section
• monolithic works continue on floors 4-5.
Underground parking lot
• work continues on landscaping between sections 1 and 2 and the installation of fire protection systems in sections 1-3.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026