Progress in construction

1
stage
100%
2
stage
95%
3
stage
80%
4
stage
30%
5
stage
20%
6
stage
0%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", December 2025

First section

•  the house is commissioned

Second section

•  facade work completed;

•  the installation of internal engineering networks and preparations for commissioning are ongoing.

Third section

•  installation of window structures has been completed;

•  facade work is ongoing (75% complete), installation of heating and water supply systems, floor screeding (30% complete), installation of railings (20% complete), installation of technical doors, installation of fire protection systems (45% complete);

•  electrical work has begun, preparation for the installation of apartment doors, preparation for finishing work.

Fourth section

•  monolithic works continue on floors 5-6;

•  preparations for bricklaying walls and partitions have begun.

Fifth section

•  monolithic works continue on floors 4-5.

Underground parking lot

•  work continues on landscaping between sections 1 and 2 and the installation of fire protection systems in sections 1-3.