First section
• the house is commissioned
Second section
• preparations for commissioning are underway.
Third section
• installation of heating and water supply systems has been completed;
• facade work (95% complete), floor screeding (85% complete), installation of railings (80% complete), installation of technical doors (95% complete), installation of fire protection systems (95% complete), electrical work (90% complete), installation of apartment doors (80% complete), and finishing work (30% complete) are ongoing.
Fourth section
• monolithic works are underway on the 8th floor and the technical floor, including the construction of walls and partitions (60% complete), preparation for window installation, and preparation for the start of installation work on the water supply and sewerage systems.
Fifth section
• monolithic works are underway on the 7th floor, including the construction of walls and partitions, and the fabrication of windows.
Sixth section
• work has begun on the foundation slab.
Underground parking lot
• work continues on landscaping between sections 1 and 2 (80% complete) and the installation of fire protection systems in sections 1-3 (95% complete);
• installation of fire protection systems has begun in section 5, and preparations for electrical work are underway.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026