Progress in construction

1
stage
100%
2
stage
100%
3
stage
95%
4
stage
55%
5
stage
45%
6
stage
8%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", April 2026

First section

•  the house is commissioned

Second section

•  preparations for commissioning are underway.

Third section

•  installation of heating and water supply systems has been completed;

•  facade work (95% complete), floor screeding (85% complete), installation of railings (80% complete), installation of technical doors (95% complete), installation of fire protection systems (95% complete), electrical work (90% complete), installation of apartment doors (80% complete), and finishing work (30% complete) are ongoing.

Fourth section

•  monolithic works are underway on the 8th floor and the technical floor, including the construction of walls and partitions (60% complete), preparation for window installation, and preparation for the start of installation work on the water supply and sewerage systems.

Fifth section

•  monolithic works are underway on the 7th floor, including the construction of walls and partitions, and the fabrication of windows.

Sixth section

•  work has begun on the foundation slab.

Underground parking lot

•  work continues on landscaping between sections 1 and 2 (80% complete) and the installation of fire protection systems in sections 1-3 (95% complete);

•  installation of fire protection systems has begun in section 5, and preparations for electrical work are underway.