Progress in construction

1
stage
100%
2
stage
100%
3
stage
99%
4
stage
75%
5
stage
65%
6
stage
10%
7
stage
5%

Progress in construction RC "Shchaslyvyi Grand", August 2026

First section

•  the house is commissioned

Second section

•  the house is commissioned

•  preparations are underway for the signing of key notarized agreements, and the process of connecting to the gas and electricity grids is in progress.

Third section

•  finishing work is underway (95% complete), along with landscaping around the building, installation of a playground, planting of greenery, and preparations for commissioning.

Fourth section

•  window installation is underway (85% complete), as are the installation of water supply and sewer systems (50% complete), exterior facade work (70% complete), roofing work, and preparations for plastering and screeding.

Fifth section

•  concrete work is underway on the floors 10-12, including the construction of walls and partitions (30% complete), and preparations for window installation.

Sixth section

•  monolithic work continues on the basement level.

Seventh section

•  the excavation work has been completed;

•  preparations for the concrete work are underway;.

Underground parking lot

•  electrical work, road marking, and final finishing touches for Phase 1 have been completed;

•  installation of fire protection systems in Section 5 is underway, along with preparations for commissioning.