First section
• the house is commissioned
Second section
• the house is commissioned
• preparations are underway for the signing of key notarized agreements, and the process of connecting to the gas and electricity grids is in progress.
Third section
• finishing work is underway (95% complete), along with landscaping around the building, installation of a playground, planting of greenery, and preparations for commissioning.
Fourth section
• window installation is underway (85% complete), as are the installation of water supply and sewer systems (50% complete), exterior facade work (70% complete), roofing work, and preparations for plastering and screeding.
Fifth section
• concrete work is underway on the floors 10-12, including the construction of walls and partitions (30% complete), and preparations for window installation.
Sixth section
• monolithic work continues on the basement level.
Seventh section
• the excavation work has been completed;
• preparations for the concrete work are underway;.
Underground parking lot
• electrical work, road marking, and final finishing touches for Phase 1 have been completed;
• installation of fire protection systems in Section 5 is underway, along with preparations for commissioning.
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: AUGUST 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
31.08.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (AUGUST 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.08.2026
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: AUGUST 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
31.08.2026