First section
• facade works, elevator installation, floor screeding, and installation of aluminum structures on the basement floor have been completed or are nearing completion;
• finishing works, landscaping around the building, and installation of radiators and heat and water meters are ongoing;
• electrical installation works have begun.
Second section
• roofing, installation of water supply and sewage systems, and plastering work in common areas have been completed.
• facade work, installation of internal engineering networks, installation of doors in common areas, and floor screeding have been completed.
• work has begun on interior finishing and elevator installation.
Third section
• the construction of walls and inter-apartment partitions, as well as the installation of the roof, has been completed;
• work is continuing on the installation of window structures, facade work, and the installation of water supply and sewage systems;
• the installation of heating systems, plastering work in common areas, and preparation for floor screeding has begun.
Fourth section
• monolithic works continue on floors 2-3.
Fifth section
• monolithic works continue in the basement, 1st and 2nd floors.
Underground parking lot
• the installation of the monolith between sections 3-5 and waterproofing between sections 1-2 are ongoing.
• landscaping between sections 1-2 and preparations for the installation of the parking lot floor have begun.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025