Progress in construction

1
stage
90%
2
stage
80%
3
stage
65%
4
stage
10%
5
stage
8%
6
stage
0%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", September 2025

First section

•  facade works, elevator installation, floor screeding, and installation of aluminum structures on the basement floor have been completed or are nearing completion;

•  finishing works, landscaping around the building, and installation of radiators and heat and water meters are ongoing;

•  electrical installation works have begun.

Second section

•  roofing, installation of water supply and sewage systems, and plastering work in common areas have been completed.

•  facade work, installation of internal engineering networks, installation of doors in common areas, and floor screeding have been completed.

•  work has begun on interior finishing and elevator installation.

Third section

•  the construction of walls and inter-apartment partitions, as well as the installation of the roof, has been completed;

•  work is continuing on the installation of window structures, facade work, and the installation of water supply and sewage systems;

•  the installation of heating systems, plastering work in common areas, and preparation for floor screeding has begun.

Fourth section

•  monolithic works continue on floors 2-3.

Fifth section

•  monolithic works continue in the basement, 1st and 2nd floors.

Underground parking lot

•  the installation of the monolith between sections 3-5 and waterproofing between sections 1-2 are ongoing.

•  landscaping between sections 1-2 and preparations for the installation of the parking lot floor have begun.