Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%
4
stage
70%
5
stage
55%
6
stage
8%
7
stage
3%

Progress in construction RC "Shchaslyvyi Grand", July 2026

First section

•  the house is commissioned

Second section

•  the house is commissioned

•  preparations are underway for the signing of key notarized agreements, and the process of connecting to the gas and electricity grids is in progress.

Third section

•  facade work, floor screeding, electrical work, and the installation of railings have been completed;

•  finishing work is underway (90% complete), along with landscaping around the building and preparations for commissioning.

Fourth section

•  the construction of walls and partitions has been completed;

•  window installation (60% complete), installation of water supply and sewer systems (40% complete), and exterior facade work (60% complete) are currently underway;

•  roofing work has begun, also the preparations for plastering and floor screeding are underway.

Fifth section

•  concrete work is underway on the 9th and 10th floors, along with the construction of walls and partitions and preparations for window installation.

Sixth section

•  monolithic work continues on the basement level.

Seventh section

•  preparations for the concrete work are underway.

Underground parking lot

•  landscaping work has been completed;

•  installation of fire protection systems in Section 5 is underway, as are electrical installation works (80% complete), and preparations for applying road markings and completing the final finishing touches on Phase 1.