The first section
• monolithic works have been completed;
• work on the ceiling of the technical floor is underway, brickwork of walls (10-12 floors), installation of glass enclosing structures (1-8 floors);
•i nstallation of internal engineering networks, roofing, and facade works have been planned.
The second section
• monolithic works have been completed;
• bricklaying of walls (10th floor) and installation of staircases are in progress.
The third section
• monolithic works are underway on the 2nd floor.
The underground parking lot
• monolithic works in 1-2 sections have been completed.
Shopping center
• installation of exterior stained glass windows;
• installation of anti-aircraft smoke removal lights;
• arrangement of internal partitions made of brick and gas block;
• installation of fire system, ventilation, air conditioning, external doors of entrance groups;
• works on external networks: water, sewerage, drainage systems.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025