1
stage
60%
The first section
• monolithic works on the 12th floor are underway;
• brickwork continues on floor 8;
• plumbing risers laying has been completed;
• preparations for the windows installation have begun.
The second section
• monolithic works are being held on the 10th floor;
• brickwork continues on the 5th floor.
The parking lot
• preparations for pouring the floor slab are underway.