Progress in construction

1
stage
100%
2
stage
95%
3
stage
80%
4
stage
30%
5
stage
20%
6
stage
0%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", June 2024

The first section

• monolithic works on the 12th floor are underway;

• brickwork continues on floor 8; 

• plumbing risers laying has been completed;

• preparations for the windows installation have begun.

The second section

• monolithic works are being held on the 10th floor;

• brickwork continues on the 5th floor.

The parking lot

• preparations for pouring the floor slab are underway.