1
stage
60%
The first section
• general construction works have been completed;
• facade works are underway (facade insulation is bonded), and works on the arrangement of internal engineering networks (storm and domestic sewage) are in progress.
The second section
• similar works are ongoing
The third section
• monolithic works are underway on the 7th floor.
The underground parking lot
• general construction works are underway