1
stage
60%
The first section
• monolithic works are underway on the 11th floor;
• brickwork is completed on floors 1-6;
• plumbing risers are being laid on floors 1-10.
The second section
• monolithic works are being held on the 7th floor and brickwork on the1st floor.
The third section
• monolithic works on the 1st floor.