1
stage
100%

The first and second sections
• glazing has been fully completed;
• engineering, communication works and ventilation piping of the risers have been processed.
The third section
• monolithic works are underway on the 7th floor.
Underground parking lot
• general construction monolithic works are underway.
Shopping center
• arrangement of the facade;
• landscaping works;
• road marking and installation of road signs have been done;
• interior finishing works;
• fire protection works;
• installation of water and electricity supply.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025