1
stage
100%

The first and second sections
• facade works, fencing of balconies and cold passages, installation of internal engineering networks are underway.
The third section
• monolithic works are underway on the 9th floor.
Underground parking lot
• the floor slab and external network works have been completed;
• the entrance to the parking lot and landscaping works on the side of Yabluneva Street are in progress.
Shopping center
• preparations for the opening are underway