1
stage
65%
The first section
• facade works, arrangement of internal engineering networks, roofing works, and internal plastering works are underway.
The second section
• facade works and the installation of internal engineering networks are ongoing;
• preparations for interior plastering work have begun.
The third section
• monolithic works on the 11th floor and brickwork on the 8th floor are underway.
Underground parking lot
• waterproofing works and monolithic works of the entrance and part of the parking lot (section 3) are underway.