Progress in construction

1
stage
65%
2
stage
60%
3
stage
45%
4
stage
0%
5
stage
0%

Progress in construction RC "Shchaslyvyi Grand", March 2025

The first section

• facade works, arrangement of internal engineering networks, roofing works, and internal plastering works are underway.

The second section

• facade works and the installation of internal engineering networks are ongoing;

• preparations for interior plastering work have begun.

The third section

• monolithic works on the 11th floor and brickwork on the 8th floor are underway.

Underground parking lot

• waterproofing works and monolithic works of the entrance and part of the parking lot (section 3) are underway.