1
stage
100%

The first section
• facade works, arrangement of internal engineering networks, roofing works, and internal plastering works are underway.
The second section
• facade works and the installation of internal engineering networks are ongoing;
• preparations for interior plastering work have begun.
The third section
• monolithic works on the 11th floor and brickwork on the 8th floor are underway.
Underground parking lot
• waterproofing works and monolithic works of the entrance and part of the parking lot (section 3) are underway.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025