Progress in construction

1
stage
60%
2
stage
40%
3
stage
30%

Progress in construction RC "Shchaslyvyi Grand", September 2024

The first section

•  general construction works have been completed;

•  engineering works (networks, sewer risers, water, heating), installation of windows, glazing are in progress;

• plastering, roofing and facade works are planned.

The second section

• general construction works and brickwork have been completed;

• brickwork of the walls (10th floor) and installation of staircases are in progress.

The third section

• monolithic works are underway on the 3rd floor.

The underground parking lot

• monolithic works between 1-3 sections have been completed.

Shopping center

• internal partitions made of brick and gas block were completed;

• installation of exterior stained glass windows;

• installation of fire system, ventilation, air conditioning, external doors of entrance groups;

• work on external networks: water, sewerage, drainage systems.

• installation of metal frame of lot partitions;

• installation of internal power grids;

• start of landscaping works.