
The first section
• general construction works have been completed;
• engineering works (networks, sewer risers, water, heating), installation of windows, glazing are in progress;
• plastering, roofing and facade works are planned.
The second section
• general construction works and brickwork have been completed;
• brickwork of the walls (10th floor) and installation of staircases are in progress.
The third section
• monolithic works are underway on the 3rd floor.
The underground parking lot
• monolithic works between 1-3 sections have been completed.
Shopping center
• internal partitions made of brick and gas block were completed;
• installation of exterior stained glass windows;
• installation of fire system, ventilation, air conditioning, external doors of entrance groups;
• work on external networks: water, sewerage, drainage systems.
• installation of metal frame of lot partitions;
• installation of internal power grids;
• start of landscaping works.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025