1
stage
100%

The first section
• reinforcement of the basement floor slab is being completed; preparations for concrete pouring are underway;
• part of the vertical of the 1st floor is poured with concrete;
• installation of the floor slab on the 1st floor is in progress.
The second section
• reinforcement of the basement floor.