Progress in construction

1
stage
100%
2
stage
100%
3
stage
95%
4
stage
65%
5
stage
50%
6
stage
8%
7
stage
3%

Progress in construction RC "Shchaslyvyi Grand", May 2026

First section

•  the house is commissioned

Second section

•  the house is commissioned

•  the process of connecting to the electricity and gas supply networks is underway, as are preparations for signing the main notarized contracts.

Third section

•  installation of fire protection systems is complete;

•  facade work (98% complete), floor screed (95% complete), installation of railings (95% complete), installation of service doors (99% complete), electrical work (95% complete), installation of apartment doors (95% complete), finishing work (55% complete);

•  landscaping work around the building section has begun, and preparations for commissioning are underway.

Fourth section

•  concrete work on the 8th floor and the technical floor has been completed;

•  work is underway on the construction of walls and partitions (80% complete), preparations for window installation, and preparations for the start of installation work on the water supply and sewer systems.

Fifth section

•  concrete work is underway on the 8th floor, along with the construction of walls and partitions and the fabrication of windows.

Sixth section

•  the foundation slab has been completed;

•  monolithic work has begun on the basement level.

Underground parking lot

•  the installation of fire protection systems in sections 1-3 has been completed;

•  work is underway on landscaping between sections 1 and 2 (80% complete), the installation of fire protection systems in section 5, preparations for electrical work, and the installation of industrial flooring.