First section
• facade works are being completed;
• finishing works, electrical works, landscaping around the building, installation of radiators, heat and water meters are ongoing.
Second section
• facade works, installation of internal engineering networks, floor screeding, interior finishing works, installation of elevators and doors are ongoing.
Third section
• facade works40% complete), installation of heating, water supply, and sewerage systems, floor screeding, installation of window structures, and plastering work in the public usage places are ongoing.
Fourth section
• monolithic works continue on floors 3-4.
Fifth section
• monolithic works continue in the basement, 2nd and 3rd floors.
Underground parking lot
• installation of the monolith between sections 3-5 is complete;
• landscaping, waterproofing and preparations for the installation of the parking lot floor between sections 1-2 have begun.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025