
The first section
• works on the arrangement of walls and partitions have been completed;
• facade works (bonded thermal insulation of the facade), glazing (10th floor), and works on the arrangement of internal engineering networks (storm and domestic sewage) are underway.
The second section
• installation of the SPOC (up to the 6th floor) is underway.
The third section
• monolithic works are underway on the 5th floor.
The underground parking lot
• excavation works, concrete preparation, and arrangement of a monolithic slab between sections 1 and 3 are underway.
Shopping center
• interior decoration of the public usage places (plastering, tiling, gypsum plastering);
• installation of internal electricity;
• installation of fire system, ventilation, air conditioning;
• improvement of the shopping center;
• laying of external networks;
• perimeter facade insulation.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025