The first section
• works on the arrangement of walls and partitions have been completed;
• facade works (bonded thermal insulation of the facade), glazing (10th floor), and works on the arrangement of internal engineering networks (storm and domestic sewage) are underway.
The second section
• installation of the SPOC (up to the 6th floor) is underway.
The third section
• monolithic works are underway on the 5th floor.
The underground parking lot
• excavation works, concrete preparation, and arrangement of a monolithic slab between sections 1 and 3 are underway.
Shopping center
• interior decoration of the public usage places (plastering, tiling, gypsum plastering);
• installation of internal electricity;
• installation of fire system, ventilation, air conditioning;
• improvement of the shopping center;
• laying of external networks;
• perimeter facade insulation.