Progress in construction

1
stage
100%
2
stage
99%
3
stage
90%
4
stage
40%
5
stage
30%
6
stage
0%
7
stage
0%

Progress in construction RC "Shchaslyvyi Grand", January 2026

First section

•  the house is commissioned

Second section

•  preparations for commissioning are underway.

Third section

•  facade work (80% complete), installation of heating and water supply systems, floor screeding (30% complete), installation of railings (30% complete), installation of technical doors and installation of fire protection systems (80% complete) are ongoing.

•  electrical work, preparations for the installation of apartment doors, and preparation for finishing work have begun.

Fourth section

•  monolithic works continue on floors 5-6;

•  preparations for bricklaying walls and partitions have begun.

Fifth section

•  monolithic works continue on floors 4-5.

Underground parking lot

•  work continues on landscaping between sections 1 and 2 and the installation of fire protection systems in sections 1-3.