1
stage
60%
The first section
• waterproofing of the basement walls and backfilling have begun.
The second section
• work with the vertical of the basement floor is being carried out;
• installation of a tower crane is planned.
The third section
• it is planned to start reinforcing and concreting the foundation slab.
Shopping center "Shchaslyvyi Mall"
• work on the central entrance group decor begins.